24th March 2009
We're off n running now. This morning the drain layers came thru with their fair share of drama due to lack of preparation and never having seen the site before.
I think they were expecting a greenfield site where the drain & sewer connections were constructed last week and just waiting to be connected too.
Instead the sewer connection was a 50 year old earthenware fitting full of crushed rock and 3m deep beside the neighbours brick wall.
In contrast the drain connection was too shallow?
Apart from all that they were done by early afternoon as the electrical connection guys came in and did their thing.